Before

Sample Problem

Calculate productivity for an excavation project:
- Equipment: CAT 336 Excavator (3.5 CY bucket)
- Material: Dense clay soil
- Average haul distance: 150 feet to dump truck
- Job efficiency: 50 minutes per hour (83%)
- Swell factor: 25%
- Operator skill: Average
- Total volume to excavate: 12,000 CY (bank measure)

Determine hourly production rate, days to complete, and cost per CY.
After

AI-Generated Solution

EQUIPMENT PRODUCTIVITY ANALYSIS

1. CYCLE TIME CALCULATION
   Bucket load time: 0.40 min
   Swing to truck (150 ft): 0.35 min
   Dump time: 0.15 min
   Return swing: 0.35 min
   Position for next load: 0.10 min
   ───────────────────────
   Total cycle time: 1.35 minutes

2. THEORETICAL PRODUCTION
   Bucket capacity: 3.5 CY
   Bucket fill factor (dense clay): 90%
   Actual bucket load = 3.5 × 0.90 = 3.15 CY

   Cycles per hour = 60 / 1.35 = 44.4 cycles
   Production (ideal) = 44.4 × 3.15 = 140 CY/hr

3. ADJUSTED PRODUCTION (Job Efficiency)
   Actual production = 140 CY/hr × 0.83 (efficiency)
   Q = 116 CY/hr (loose measure)

   Convert to bank measure:
   Q_bank = 116 / 1.25 (swell factor)
   Q_bank = 93 CY/hr (bank measure)

4. PROJECT DURATION
   Total volume: 12,000 CY (bank)
   Production rate: 93 CY/hr

   Hours required = 12,000 / 93 = 129 hours
   Days required = 129 / 8 = 16.1 days

   Use 17 working days

5. COST ANALYSIS
   Equipment rental: $185/hr
   Operator wage: $45/hr
   Fuel (15 gal/hr @ $3.50/gal): $52.50/hr
   Maintenance allowance: $18/hr
   ───────────────────────
   Total hourly cost: $300.50/hr

   Cost per CY = $300.50 / 93 CY
   Cost per CY = $3.23/CY

   Total project cost = 129 hrs × $300.50
   Total cost = $38,765

PRODUCTIVITY SUMMARY:
✓ Production rate: 93 CY/hr (bank measure)
✓ Project duration: 17 days
✓ Cost per CY: $3.23
✓ Total equipment cost: $38,765

Key Results

Production Rate
93 CY/hr
Project Duration
17 days
Cost per CY
$3.23
Total Cost
$38,765

Common Use Cases

Cost estimating
Schedule planning
Equipment selection
Bid preparation

Professional Review Required

This demo shows AI-generated output for preliminary design purposes only. All calculations must be verified by a licensed Professional Engineer (PE). Cognitive BuiltWorld assumes no liability for designs based on AI outputs.

Get Full Access to This Tool

Premium members get the complete prompt text, multiple templates, advanced features, and priority support.